Greetings Experts,
could You, pls help me to find out how system automatically select its application, when creating a BOM; I mean I need to select applications when list it via CS12; actually I do not really care the CS12, I care the BOM selection at Prod Order.
No generic answer, please, I have read avlbl Helps already, and still asking
I have the follwoing example:
OS30 - Applications
PP01 as applicatioin has Sel ID 01 (still standard set)
ZSED Sel ID 01
SD01 Sel ID 04 (still standard set)
OS31 Order priority for BOM usage
Sel ID 01 - SelPr1 - usage1; SelPr2 - usage3
SelID 04 SelPr1 - usage 5, SelPr2 - usage 3, SelPr3 usage 7
Created a BOM via CS01 usage 3 , and automatically get ZSED application in CS12;
when deleted the ZSED application, the new BOM had an application SD01
never PP01;
Why I have this situation, could not figure it out.
Anyone of You, pls explaine what I miss here?
Thanks in advance
LM