Hello Experts
I'm facing the follonwing issue :
Client first did not want PR+Reservation when assigning Material requirement to his WBS. he only wants PR then we changed the item category from L (stock item) to N (Non stock item).
Example :
1/ Activity A asked for 150 cement bags
2/ PR created with qty 150, item category "N". No reservation created on stock
3/ We transform PR in PO, and MIGO for good receipt
4/ We're now ready ask logistics to send us these 150 cement bags so we made a manual reservation
ISSUE : we're not supposed to make a reservation superior than 150 cement bags, however users are able to ask 200 or 300 cements bags for network.
Thanks for your help
Regards